1.
Submit ten (10) copies of Preliminary Plans,
or Minor Final Subdivision Plans, or Site Plans to
the Planning and Development Department, City
Administration Building, 233 West Gaines Street, NBU
#4, Lawrenceburg, TN 38464 by 12:00 Noon,
Twenty-one (21) days prior to the Planning
Commission Meeting, (the second Thursday of each
month).
2.
Preliminary Plans are dispersed to utilities,
reviewing engineer, State Planner, and others, as
needed for comments.
3. All
Subdivision Plat fees and Site Plan Review fees must
be paid before your project will be placed on the
Planning Commission’s Agenda.
4.
Developer
submits five (5) copies of Construction Plans and
Plat by 12:00 Noon, Twenty-one days prior to the
next regular meeting of the Planning Commission
(second Thursday of each month). Developers pay
construction plan fees. Submittals not received by
12:00 Noon will not be accepted for review.
5.
Ten (10) copies of Final Plat must be
submitted within one (1) year from approval of
Preliminary Plat. Developers pay Final Plat fees.
6. Submittals
that are significantly incomplete may not be
accepted at the time of submittal, and/or may not be
considered by the Planning Commission.
7.
Approval or disapproval of Final Plat by
Planning Commission.
8.
Improvements must be constructed or bonds
posted before final plat is recorded.
9.
Building Official will collect recording
fees of $16.00 (storm water detention agreement),
$5.00 (8 ˝ X 14” plat), $10.00 (18”X24”), $15.00
(24”x30”) and record documents at R.O.L.C.
10.
A check list is included in a package that
may be picked up at the Planning and Development
Office to assist in noting appropriate items before
submitting your plans. The Storm Water Management
Ordinance is also a part of this package. |